|
A world leader
A world leader in
pharmaceuticals contacted Honeyman Group to provide a solution for
upgrading an aged autoclave and dry heat oven. The equipment
was in
good mechanical order but the controls, instrumentation and
ancillary equipment were becoming unreliable, unsupportable and not
regulatory compliant (control system validation and data integrity).
The pharmaceutical company
had 3 problems; Time, Upheaval and Cost.
1.
Time:
The pharmaceutical company had looked into
replacing the autoclave and oven with new. The complete project
timescale for replacing the existing autoclave and oven, from
order placement to end of validation would be in the region of
14 months. In addition, the actual outage time for removing the
existing autoclave and oven, replacing with new equipment,
rebuilding the clean room etc would be a minimum of 3 months.
Production lost for this amount of time would be completely
unacceptable.
2.
Upheaval:
The autoclave was situated in a class 10,000
sterile environment. To remove the autoclave and oven from
their existing location, with new walls, offices, built around
the autoclave since its original installation, would be a
mammoth job. The area would become non-sterile and production
could not start again until the area was fully rebuilt, finished
and validated.
3.
Cost:
The total cost of the project to replace the
existing autoclave and oven, including all of the building works
and other validation implications would be in the region of
£500k, not to mention the sales/production impact of such a
project.
Honeyman were approached to
provide a solution to overcome these problems. The first challenge
was to assess the autoclave and oven for their condition, mechanics
and future reliability. The old machines had very good chambers and
mechanics but the control systems and instrumentation were fast
becoming unsupportable and would dictate the life of the machines.
The solution was to provide
a new, modern control system with updated instrumentation. Also to
fully refurbish the plant room areas in terms of cabling, pneumatics
and overall system documentation (FDS, SDS, drawings etc).
From start to finish,
Honeyman Group managed the project, liaising with the Client's
Quality, Engineering and Process departments logging all comments
and requirements and keeping all informed of the progress of the
project.
Following a full survey of
the autoclave and oven, which included physical data and functional
performance, Honeyman Group produced a new Functional Design
Specification (FDS) for both the autoclave and oven. The new
control system developed to meet this FDS was based upon a Eurotherm
T800 visual supervisor and a T2550 controller.
By choosing to upgrade only
the parts of the equipment that required upgrading this minimised
the disruption to the area. The shutdown period from removal of the
redundant equipment through to completing the engineering validation
(IQ and OQ) on both the oven and the autoclave in parallel took only
4 weeks and the cost was significantly lower than the cost for a
replacement autoclave and oven. All documentation was handed over
within 2 weeks of completion.
The client was left with a
fully documented, validated autoclave with an up to date control
system developed using the GAMP4 guidance and taking account of the
requirements of 21 CFR part 11 for data integrity and tracking
changes.
|